Negative cash flow probably causes more construction companies to run into financial trouble (leading to their closure) than any other cause.
Even a profitable construction project can cause a company financial problems if the cash flow is negative.
Negative cash flow is when the construction company is paying money to suppliers, equipment hire companies and subcontractors, or in wages and salaries, before the client has paid for the work that has been completed.
Unfortunately most construction projects are usually cash negative to some extent. Many clients hold 10% cash retention until the end of the project when this is reduced by half. Consequently if the project is tendered at anything less than a 10% profit the project is usually cash negative until the end.
In addition, most clients only pay the contractor thirty days after the contractor submits an invoice. These invoices are normally submitted at the end of each month. Many contractors pay their workers fortnightly or in some cases weekly. This could mean the contractor has paid out up to seven weeks of wages before the client pays for the work that these personnel have completed. Smaller contractors sometimes have to pay suppliers before they will release materials.
What Makes Cash Flow Even Worse?
There are, however, a number of other factors that make the cash flow situation even worse:
- Many construction projects have payment terms longer than thirty days.
- In addition some clients habitually pay progress claims late or not in full.
- Of course, the ultimate knockout blow for many construction companies is when clients don’t pay at all. This could be a result of the client disputing the value of work, defaulting on the contract or going into liquidation.
Yet, even with the odds stacked against construction companies, they often make their cash flow situations worse by submitting their progress valuations late, accepting payments late or not claiming fully for completed work.
How To Improve Cash Flow Situation
To improve the cash flow situation construction companies must submit their monthly progress valuations on or before the due date. Some clients only run progress payments on a particular day in the week, or month, so missing a submission date could cause the client to delay payment by up to a month. The valuations must be submitted in the required format and with the required supporting documentation since many clients will use any excuse to delay or reject a monthly claim.
It’s important to track the progress of the payment through the client’s payment system. With major clients there may be several people that check and approve the valuation and payment. Sometimes, the process is disrupted when someone is absent, or the claim simply gets ‘lost’. I’ve had more than one client who consistently paid progress claims late, always with some excuse about our valuation being late, the claim being incorrect (either arithmetic errors, insufficient supporting documentation or disagreement with our progress) and people in the approval process being absent. Of course many of these problems were only reported to us when the payment was due, despite the client having had the claim for thirty days.
Some contracts are structured such that payments are only made when the contractor achieves particular milestones. It’s important that Project Managers understand what these milestones entail and ensure they are met. It’s obviously pointless to achieve 99% completion if payment is only made for 100%. Often contractors take several weeks to complete the last few items (which may just be completing documentation), which delays payment.
(Written by Paul Netscher the author of the acclaimed books ‘Successful Construction Project Management: The Practical Guide’ and ‘Building a Successful Construction Company: The Practical Guide’. Both books are available in paperback and e-book from Amazon and other retail outlets. This article is adapted from information included in these books. To read more visit www.pn-projectmanagement.com )
© 2015 This article is not to be reproduced for commercial purposes without written permission from the author